Preventive Maintenance Pada Mesin Cabling
Preventive Maintenance Pada Mesin Cabling
Nama Kelompok :
UNIVERSITAS GUNADARMA
MAINTENANCE PADA MESIN CABLING
1Langkah Pengecekan
TAKE UP
1.) Fungsi & kebersihan Blower main motor
2.) Fungsi & posisi Limit / proximity switch
3.) Fungsi & terminasi Main motor & drive / control
4.) Fungsi & terminasi Motor bobbin
5.) Fungsi & terminasi Pelumasan & visual ulir
6.) Volume & temperatur Level oil & temperatur gear box
7.) Fungsi & dimensi system rem & kanvas
8.) Fungsi & dimensi Belt / couple system
9.) Fungsi & kebersihan Adaptor system
10.) Kekencangan / ulir baut
11.) Fungsi & kebersihan Solenoid valve
12.) Fungsi safety mesin
CAPSTAN/CATERPILLAR
1.) Fungsi & kebersihan Blower main motor
2.) Fungsi & terminasi Main motor & drive / control
3.) Volume & temperature Level oil & temperatur gearbox
4.) Fungsi & dimensi Belt / couple system
5.) Fungsi & tekanan Silinder & angina system
6.) Fungsi & kebersihan Roller system & pelumnas gear
7.) Kekencangan / ulir baut
8.) Fungsi & kebersihan Solenoid valve
CAGE MACHINE
1.) Fungsi & kebersihan Blower main motor
2.) Fungsi & terminasi Main motor & drive / control
3.) Volume & temperatur Level oil & temeperatur gear box
4.) Fungsi & dimensi Belt / couple system
5.) Fungsi & kebersihan Guide / roller system
6.) Fungsi & dimensi system rem & kanvas
7.) Kekencangan / ulir baut
8.) Fungsi & kebersihan solenoid valve
PENGUKURAN & PROTEKSI
1.) Fungsi & terminasi Counter
2.) Fungsi & terminasi Wire break
3.) Fungsi & terminasi Safety switch / proximity
4.) Fungsi & terminasi emergency stop
5.) Fungsi & kebersihan Filter / lubricator
6.) Fungsi & tekanan angin & regulator
7.) Kekentalan & kebersihan Penggantian oil gear box
PANEL CONTROL / OPERATOR
1.) Fungsi & kebersihan Kipas / pendingan /AC
2.) Terminasi & kebersihan Komponen komponen listrik
3.) Terminasi & kebersihan Terminal
2. Tujuan Pengcekan
TAKE UP
Tujuan pengecekan dan perbaikan ini untuk tidak terjadinya composite core kehilangan tension yang akan membahayakan pekerja karna akan mengakibatkan core berputar cepat.
CAPSTAN / CATERPILLAR
Tujuan pengecekan dan perbaikan ini untuk cengkraman dan tarikan pada caterpillar tetap berfungsi .
CAGE MACHINE
Tujuan pengecekan dan perbaikan ini untuk menjaga kabel-kabel tersebut tetap aman
PENGUKURAN & PROTEKSI
Tujuan pengecekan dan perbaikan ini untuk sistem pengamanan pada kabel-kabel
PANEL CONTROL / OPERATOR
Tujuan pengecekan dan perbaikan ini untuk sistem kontrol otomatis dan proses tetap stabil dan bisa digunakan.
- Alfian Priliambodo
- Dian Wahyudin
- Ikhsan Fadillah
- Marysca Shintya Dewi
- Yoga Bara Gunawan
UNIVERSITAS GUNADARMA
MAINTENANCE PADA MESIN CABLING
1Langkah Pengecekan
TAKE UP
1.) Fungsi & kebersihan Blower main motor
2.) Fungsi & posisi Limit / proximity switch
3.) Fungsi & terminasi Main motor & drive / control
4.) Fungsi & terminasi Motor bobbin
5.) Fungsi & terminasi Pelumasan & visual ulir
6.) Volume & temperatur Level oil & temperatur gear box
7.) Fungsi & dimensi system rem & kanvas
8.) Fungsi & dimensi Belt / couple system
9.) Fungsi & kebersihan Adaptor system
10.) Kekencangan / ulir baut
11.) Fungsi & kebersihan Solenoid valve
12.) Fungsi safety mesin
CAPSTAN/CATERPILLAR
1.) Fungsi & kebersihan Blower main motor
2.) Fungsi & terminasi Main motor & drive / control
3.) Volume & temperature Level oil & temperatur gearbox
4.) Fungsi & dimensi Belt / couple system
5.) Fungsi & tekanan Silinder & angina system
6.) Fungsi & kebersihan Roller system & pelumnas gear
7.) Kekencangan / ulir baut
8.) Fungsi & kebersihan Solenoid valve
CAGE MACHINE
1.) Fungsi & kebersihan Blower main motor
2.) Fungsi & terminasi Main motor & drive / control
3.) Volume & temperatur Level oil & temeperatur gear box
4.) Fungsi & dimensi Belt / couple system
5.) Fungsi & kebersihan Guide / roller system
6.) Fungsi & dimensi system rem & kanvas
7.) Kekencangan / ulir baut
8.) Fungsi & kebersihan solenoid valve
PENGUKURAN & PROTEKSI
1.) Fungsi & terminasi Counter
2.) Fungsi & terminasi Wire break
3.) Fungsi & terminasi Safety switch / proximity
4.) Fungsi & terminasi emergency stop
5.) Fungsi & kebersihan Filter / lubricator
6.) Fungsi & tekanan angin & regulator
7.) Kekentalan & kebersihan Penggantian oil gear box
PANEL CONTROL / OPERATOR
1.) Fungsi & kebersihan Kipas / pendingan /AC
2.) Terminasi & kebersihan Komponen komponen listrik
3.) Terminasi & kebersihan Terminal
2. Tujuan Pengcekan
TAKE UP
Tujuan pengecekan dan perbaikan ini untuk tidak terjadinya composite core kehilangan tension yang akan membahayakan pekerja karna akan mengakibatkan core berputar cepat.
CAPSTAN / CATERPILLAR
Tujuan pengecekan dan perbaikan ini untuk cengkraman dan tarikan pada caterpillar tetap berfungsi .
CAGE MACHINE
Tujuan pengecekan dan perbaikan ini untuk menjaga kabel-kabel tersebut tetap aman
PENGUKURAN & PROTEKSI
Tujuan pengecekan dan perbaikan ini untuk sistem pengamanan pada kabel-kabel
PANEL CONTROL / OPERATOR
Tujuan pengecekan dan perbaikan ini untuk sistem kontrol otomatis dan proses tetap stabil dan bisa digunakan.
1 komentar: